LNG plant construction a huge undertaking

Alaska LNG project teams played it by the numbers — really big numbers — in a presentation on construction plans to federal, state and municipal officials:

Site preparations for the proposed liquefied natural gas plant and massive LNG storage tanks in Nikiski would require stripping up to 4 million cubic yards of loose soil, soft peat moss and other vegetation. That’s more than enough to cover a rough trail 10 feet wide, a foot deep from New York City to Houston.

Crews would then need to excavate as much as 6 million cubic yards of frost-susceptible material — up to 6 feet deep in some areas — to prepare the site for construction. Some of the material could be reused as fill, while other material would need to be trucked in to complete the base.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The two domed LNG storage tanks would each measure 305 feet in diameter, more than large enough for a Boeing 747 to spin around inside without scraping its wings.

All of the numbers are approximate and subject to change as the project teams refine the design, they reminded participants at workshops held Sept. 2 and 3 in Anchorage. More than 20 Alaska LNG project team members were at the workshops to brief government agency officials and answer questions.

Add in the jetty, the twin loading berths for LNG carriers and other components of the Nikiski project, and the preliminary numbers continue adding up:

The project would use 800,000 cubic yards of gravel, 300,000 cubic yards of concrete, 300,000 cubic yards of armor rock, 100,000 tons of structural steel, 6,500 pilings, 7 miles of electrical wiring, almost 200 miles of aboveground piping, and 20 miles of buried pipe.

The trestle to reach the loading berths could be as much as 3,200 feet long — more than half a mile — to reach water deep enough for the LNG carriers to safely maneuver.

Though no substantial dredging would be needed for the jetty and loading berths, an estimated 1 million to 2 million cubic yards of dredging would be required at the temporary dock that would be built for offloading materials from barges and heavy-lift vessels during construction.

The 250-megawatt, gas-fired power plant at the LNG plant site would generate enough electricity to run a city of several tens of thousands of homes.

Peak construction workforce at the Nikiski site would be 4,000 to 6,000 workers.

Planning work continues

The LNG team reported that ongoing engineering and construction planning includes several goals: Limit truck traffic in the area as much as possible, limit dredging as much as possible, and maintain public access throughout the area as much as possible.

The informational workshops were part of a series provided by Alaska LNG for regulatory agencies. The project partners — ExxonMobil, BP, ConocoPhillips, TransCanada and the state of Alaska — plan to submit their second draft of environmental and engineering reports to the Federal Energy Regulatory Commission in first-quarter 2016. The final reports and complete project application could come third-quarter 2016 as the partners work through regulatory and permit issues for the $45 billion to $65 billion project to move Alaska North Slope gas to market.

In addition to the LNG plant at Nikiski, the project includes 806 miles of pipeline to reach the plant site from North Slope gas fields and a gas treatment plant to remove carbon dioxide and other impurities before the gas enters the pipeline.

Alaska LNG has been buying up property around the proposed plant site in Nikiski, accumulating ownership or options on about 600 acres of the 800 to 900 acres needed for the operation. Team members reported that demolition could start later this month on some structures. They also are doubling their security patrols in the area in response to community concerns.

The actual footprint for the LNG plant, storage tanks, power plant and other support buildings would total approximately 200 to 300 acres. The teams explained that the rest of the land is to provide a safety, noise and light buffer for neighboring property owners, plus work space to support the construction effort.

Offloading facility comes first

There is a lot of work to get to that first cargo.

Before significant construction could begin, the material offloading facility would need to be built. The current plan, subject to change, has it just north of the LNG carrier jetty. With a 1,500-foot-wide frontage for offloading from heavy-lift vessels (called lift-on, lift-off) and a side facility with a 500-foot face for roll-on, roll-off deliveries, the freight dock could see 250 LNG plant modules delivered by 60 ships over a three-year period. Riprap — heavy rocks stacked atop each other — would be installed on either side of the facility to protect the shoreline.

Each prebuilt module could weigh as much as 6,000 tons. Self-propelled modular trailers would haul the huge pieces to the plant site.

The freight dock would be dismantled at the end of the project.

Water depth at the proposed site for the offloading facility is only about 15 feet and would need to be dredged to 30 feet, the teams said. Estimates are that would require moving 1 million to 2 million cubic yards from the seabed. “We are continuing to study how we can minimize that,” a team leader said. The dredged area would measure about 3,200 feet by 1,500 feet, depending on the final design and seabed slope.

The project continues to collect data on currents, waves, sediment, sea floor bathymetry and other conditions in the area. There are plans to excavate a sample pit in the seabed in the second quarter 2016 to measure how much and how quickly it fills in.

Disposal sites for any dredging material are still being considered, including upland and at sea. Upland disposal could be used to protect the shoreline from erosion or for fill at the project site. Any decisions on disposal sites will be based on the composition of the dredged spoils and in close consultation with government agencies.

In an effort to limit truck traffic on heavily traveled Kenai Peninsula highways, the teams reported that as much as possible construction materials arriving in Anchorage or Seward would be barged to Nikiski.

Construction site services

Even before the material offloading facility is under full construction, Alaska LNG would build “pioneer camps” at the plant site, the first housing for the first work crews. During construction, until the project builds its own power generating plant, Alaska LNG may buy electricity from a local provider — that’s one of the issues still undecided.

Currently, Alaska LNG plans to drill its own water wells, estimating its maximum needs during peak construction at almost 400,000 gallons a day, or enough for 4,000 to 5,000 people, according to U.S. government water-use estimates.

Current plans indicate no water would be withdrawn from Cook Inlet for plant operations, the teams said. The liquefaction equipment would be air-cooled, not water-cooled.

Alaska LNG plans to build a secondary-level treatment plant on site for domestic sewage, and is still looking at options for proper disposal of industrial waste.

The mission statement for handling construction waste is “reduce, reuse and recycle,” with the teams reporting there could be an estimated 7,500 tons of wood waste in addition to the 4 million cubic yards of vegetation from site clearing. The teams are working to determine “what can be handled locally, what can be handled on site, what has to be hauled away.”

 

This update, provided by the Kenai Peninsula Borough mayor’s office, is part of an ongoing effort to help keep the public informed about the Alaska LNG project. Larry Persily is a special assistant for oil and gas issues to borough Mayor Mike Navarre.

More in Life

File
Minister’s Message: Finding love in the pits

Navigate your way out of the mire of life with the love and grace of Jesus Christ.

Dancers rehearse Forever Dance’s 10th Anniversary Company Showcase, “Down Memory Lane,” at Kenai Central High School in Kenai, Alaska, on Wednesday, March 26, 2025. (Jake Dye/Peninsula Clarion)
Forever Dance comes full circle

The anniversary show will feature returning appearances from alumni and messages from former coaches.

Poopdeck Platt fishes with friends in this undated photograph. (Photo courtesy of Ken Moore)
Poopdeck: Nearly a century of adventure — Part 7

By the late 1970s, Poopdeck was already investing in stocks and bonds.

Virginia Walters (Courtesy photo)
Life in the Pedestrian Lane: Turn the radio on

Radio had something for everyone.

This tuna casserole calls for peas, parsley and Parmesan incorporated into a sturdy pasta. (Photo by Tressa Dale/Peninsula Clarion)
Quick and kid-pleasing casserole

This wholesome dish is great for busy families and fussy eaters.

The cast of the Kenai Performers’ production of “The Mousetrap” rehearse at the Kenai Performers Theater near Soldotna on Wednesday. (Jake Dye/Peninsula Clarion)
Performers set murderous ‘Mousetrap’

The longest-running stageplay in history, the English whodunit challenges audience to unravel the plot.

These monster cookie-inspired granola bars are soft, chewy and tasty enough to disguise all the healthy nuts, oats and seeds. (Photo by Tressa Dale/Peninsula Clarion)
Fueling the fearless

My son’s adventurous nature unfortunately does not extend to his diet.

Clarence Hiram “Poopdeck” Platt sits atop a recent moose kill. (Photo from In Those Days: Alaska Pioneers of the Lower Kenai Peninsula, Vol. II)
Poopdeck: Nearly a century of adventure — Part 6

Poopdeck Platt was nearly 80 when he decided to retire from commercial fishing.

Nick Varney
Unhinged Alaska: It can’t be break-up ‘cause there was no winter

I meditate a lot. Sometimes up to several seconds at once. Last… Continue reading

Most Read