AP Photo/Frank Flavin/Alaska Energy Authority In this 2012 file photo, researchers walk along the Susitna River. With a spending freeze lifted by Gov. Bill Walker, work is resuming on the Susitna-Watana hydroelectric project. However, the authority will need about $100 million in new funding to get through the Federal Energy Regulatory Commission licensing process and to construction.

AP Photo/Frank Flavin/Alaska Energy Authority In this 2012 file photo, researchers walk along the Susitna River. With a spending freeze lifted by Gov. Bill Walker, work is resuming on the Susitna-Watana hydroelectric project. However, the authority will need about $100 million in new funding to get through the Federal Energy Regulatory Commission licensing process and to construction.

Susitna-Watana studies resume after spending freeze lifted

  • By ELWOOD BREHMER
  • Saturday, August 15, 2015 7:42pm
  • News

Work is resuming on the Susitna-Watana hydroelectric project under spending guidelines put in place by Gov. Bill Walker’s administration.

The overall cost for the proposed 705-foot dam in the upper reaches of the Susitna River has been pegged at $5.6 billion in 2014 dollars by the Alaska Energy Authority, or AEA.

AEA will need $105 million, maybe more, to get through the Federal Energy Regulatory Commission licensing process and to construction, authority Executive Director Sara Fisher-Goad said during an Aug. 6 board meeting. However, AEA only has the ability to spend the $6.6 million it has in the bank for the project through 2017. That money should get the project to the study plan determination, at which point FERC would rule whether or not the authority has gathered sufficient relevant data to apply for a project license. The FERC license is the last and largest pre-construction hurdle.

Fisher-Goad said AEA will continue to update data with field studies as necessary to prevent work from becoming stale or outdated.

National Marine Fisheries Service officials have questioned the validity of some Susitna-Watana fisheries studies.

“The longer we stretch this out, we’re losing our economy of scale to be able to have logistics support on several studies at one time,” she said. “We’re doing this in more of an incremental fashion.”

AEA has completed 14 of 58 FERC-approved studies so far, according to Dyok. To date, the project has received $192 million in state appropriations. The Walker administration lifted an administrative order July 6 that halted spending on the dam.

one of six large infrastructure projects that were put on hold in late December.

After 2017, once AEA has exhausted its funds for working towards a study plan determination, “the project will be revisited in the context of the fiscal environment and other competing major capital projects,” Office of Management and Budget Director Pat Pitney wrote in a memo to Fisher-Goad.

Mike Wood, president of the lead Susitna-Watana opposition group the Susitna River Coalition, in a July 16 release, called resuming the project a “slap in the face” to Alaskans as state leaders discuss ways to increase state revenue during a time of multi-billion dollar budget deficits.

“The proposed dam has already wasted hundreds of millions of state dollars and needs to be immediately shut down,” Wood said. “It diverts necessary funds for other, more responsible and reasonable alternative energy developments, as well as goes against Walker’s campaign promises of fiscal responsibility and fish-first policies.”

AEA has touted the dam, which would generate about 2,800 gigawatts, as a way to provide half of the Railbelt’s energy demand with clean energy at long-term stable prices.

Continuing at a slower pace to prevent unnecessary spending could end up costing the state if the dam is ultimately built, AEA Project Manager Wayne Dyok said at the AEA board meeting.

At $5.6 billion to build today, inflation on project financing could add up to $150 million to the cost each year construction is delayed, he said.

If everything goes according to the current plan, AEA will be able to submit its license application with FERC in 2019, and hopefully begin construction soon after a typical two-year review, according to Dyok. However, if AEA gets the $100 million-plus it needs to submit its application before 2017, that timeline could be accelerated by two years and potentially save the state $300 million.

The cost of financing the project could also have a direct impact on long-term electric rates.

“What you get out of a constructed hydro project is this inflation-proof aspect, but you don’t get that until it’s constructed and generating,” Fisher-Goad said.

Dyok said the dam would save Railbelt consumers an average of $224 million per year on energy costs over the first 50 years in production, a total savings of $11.2 billion over that time.

Initial electric rates from Susitna-Watana — with first power in 2029 — would be in the 13 cents per kilowatt-hour range, AEA estimates.

That price would continue to drop to an average of 6.6 cents per kilowatt-hour as about $8 billion in principal plus interest is paid off over 50 years. By contrast, natural gas-generated electricity from the large Alaska LNG Project would be about 11 cents per kilowatt-hour in 2029 and increase to a more stable rate of about 15 cents per kilowatt-hour over several decades, according to Alaska Center for Energy and Power projections.

On the energy savings alone, Dyok said the cost-benefit ratio for the project is 2.39-to-1. When the avoided cost of building new gas-fired generating capacity, generation facility retirement, and greenhouse gas reductions are included, the ratio improves to more than 3-to-1, he said.

Roughly half of the project qualifies for a U.S. Department of Agriculture Rural Utilities Service loan, which is conservatively projected with 4 percent interest, Dyok said.

The rest of the project financing is planned as nearly $4 billion paid in state bonds at 5 percent interest over 30 years a portion of which would be refinanced at a lower rate, according to AEA officials.

As an added bonus, Susitna-Watana would generate billions for Alaska’s economy during construction along with clean, affordable power once its turbines are turning, AEA claims.

The dam would have an economic impact of $3.4 billion and generate about 1,300 jobs each year during construction, according to a Northern Economics study commissioned by the authority.

Preconstruction study work has generated jobs, but also information that is being used by other state agencies.

“This project has advanced the state of science for a number of agencies, particularly the Alaska Department of Fish and Game through some of the salmon work,” Dyok said.

Fish and Game Mat-Su area sport fish biologist Richard Yanusz said in an interview that AEA’s funding for fisheries studies has provided significant benefit to the department. He said there is relatively little data on chinook salmon in the Susitna drainage, despite the popularity of the species.

AEA’s studies in 2013-14 provided drainage-wide abundance estimates through radio telemetry tracking and mark-recapture efforts.

According to Yanusz, some of that information had not been gathered since the first time Susitna-Watana was proposed in the 1980s.

“It’s been a long time between those abundance estimates, so having such a basic piece of information is very helpful to management,” he said. “It is almost new information, very rare information, so just having those reference points will be helpful.”

Similar studies were done for coho salmon, the other primary sport fish in the drainage, on the main stem of the Susitna, without including the major tributaries such as the Yentna.

Dyok said the Department of Natural Resources has also found flow data helpful for other potential projects in the region.

Managing flow below the dam has been an issue of contention for those opposed to Susitna-Watana, because of the potential impacts to juvenile salmon, particularly in winter.

AEA is developing models to better project flow regimes throughout the year, but how much water is let through the dam is ultimately regulated by FERC, according to Dyok.

Average winter flow at the dam site would increase about four times and roughly be cut in half during the summer to retain water during times of lower electric demand based on early projections, he said.

Flow at the dam site currently comprises about 16 percent of the average annual water in the Susitna.

“Fisheries, recreation, and power; you need to balance all of those factors,” Dyok said.

Elwood Brehmer can be reached at elwood.brehmer@alaskajournal.com.

More in News

State House District 6 candidates Rep. Sarah Vance, Dawson Slaughter and Brent Johnson participate in a candidate forum hosted by the Peninsula Clarion and KBBI 890 AM at the Homer Public Library in Homer, Alaska, on Tuesday, Oct. 29, 2024. (Jake Dye/Peninsula Clarion)
Saturday update: House District 6 race tightens slightly in new results

Neither incumbent Rep. Sarah Vance or challenger Brent Johnson have claimed 50% of votes in the race

A grader moves down 1st Avenue in Kenai, Alaska, during a snow storm on Tuesday, Feb. 28, 2023. (Jake Dye/Peninsula Clarion)
Storm system to bring weekend snow to western Kenai Peninsula

Extended periods of light to moderate snow are expected Friday through Sunday morning

Homer Electric Association Chief Operating Officer Rob Montgomery speaks during a joint luncheon of the Kenai and Soldotna Chambers of Commerce at the Kenai Chamber of Commerce and Visitor Center in Kenai, Alaska, on Wednesday, Nov. 13, 2024. (Jake Dye/Peninsula Clarion)
HEA talks search for new energy sources, hazard trees at chamber luncheon

The utility produces 90% of its electricity using natural gas

Alaska State Troopers logo.
Update: Troopers arrest Anchor Point man wanted on felony warrants

Troopers sought help from the public in a search for Tanner Allen Geiser

From left: Joseph Miller Jr. and Jason Woodruff, Alaska State Troopers charged with felony first-degree assault, appear with their lawyers, Clinton Campion and Matthew Widmer, for an arraignment at the Kenai Courthouse in Kenai, Alaska, on Thursday, Nov. 14, 2024. (Jake Dye/Peninsula Clarion)
Troopers renew not guilty pleas after grand jury indictment

Woodruff, Miller charged with felony first-degree assault for alleged conduct during May arrest in Kenai

Canna Get Happy owner Sandra Millhouse, left, appears with attorney Richard Moses during a meeting of the Board of Adjustment at Kenai City Hall in Kenai, Alaska, on Oct. 15, 2024. (Jake Dye/Peninsula Clarion)
Kenai board of adjustment denies Canna Get Happy appeal

The owner sought to operate a retail marijuana establishment at Swanson Square in Kenai

A winter weather advisory and special weather statement are in effect for the western Kenai Peninsula, while other messages are published for the eastern Kenai Peninsula, in this map from the National Weather Service. (Screenshot/National Weather Service)
Snowfall, heavy winds forecast for tonight

Winter weather advisory and other messages from National Weather Service effective through Friday morning

The storefront of Madly Krafty in Kenai, Alaska, is seen on Thursday, Nov. 14, 2024. (Jake Dye/Peninsula Clarion)
Soldotna Chamber of Commerce holds 5th annual Spark event

Soldotna sharks give $4,000 scholarship to local gift shop

Kenai Peninsula Borough School District Superintendent Clayton Holland speaks during a meeting of the KPBSD Board of Education in Soldotna, Alaska, on Monday, June 3, 2024. (Jake Dye/Peninsula Clarion)
School board considers ‘hypothetical’ 4-day calendar, asks for community survey

Included in the work session notes is a potential calendar describing weeks running from Monday to Thursday starting in August 2025

Most Read