An area cleared for the Cooper Landing Bypass Project can be seen below Slaughter Ridge in Cooper Landing, Alaska, on July 18, 2020. (Jeff Helminiak/Peninsula Clarion)

An area cleared for the Cooper Landing Bypass Project can be seen below Slaughter Ridge in Cooper Landing, Alaska, on July 18, 2020. (Jeff Helminiak/Peninsula Clarion)

Expect delays when traveling through Cooper Landing this summer

Work will focus on the first 2 miles of the project, near the west end of the existing alignment.

Summer work on the Cooper Landing Bypass Project will range from widening lanes to cultural preservation and is expected to cause some traffic delays in the area.

The project aims to alleviate congestion on the Sterling Highway, bring some existing roads up to current highway design standards and improve highway safety. The project will see the construction of about 10 new miles of roadway, beginning at Milepost 46.2 and ending at Milepost 56 of the Sterling Highway. Final completion of the bypass is not expected until 2025.

Travelers on this section of the Sterling Highway this summer should expect some traffic delays as the state works on the west end alignment, near Milepost 56. Project Manager Sean Holland with the Alaska Department of Transportation and Public Facilities said Monday that work will focus on the first 2 miles of the project, near the west end of the existing alignment.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Work will include upgrading the existing roads to meet current rural highway standards, including widening lanes to 12 feet and shoulders to 8 feet. Retaining walls and wildlife crossings are also part of the planned work. Holland said they want to schedule work at night and around weekends to keep disruptions to regular traffic flow as minimal as possible, but that people should still expect delays.

“There’s going to be some significant traffic delays there probably this summer — no ‘probably’ about it, I guess,” Holland said.

Another element of the work planned for this summer, Holland said, is collaboration between the DOT and the Kenaitze Indian Tribe. Part of the new alignment goes through the Squilantnu Archaeological District, including some known historical sites. Holland said that a team of archaeologists surveyed the area last summer and were able to roughly define the boundaries of some of the sites. Still, Holland said, the project will not be able to avoid the area entirely.

“We were able to import that into our highway design so that, as much as possible, we can avoid those areas with our highway,” Holland said. “Some of those areas are just not avoidable; we’re going to impact them.”

Another team of archaeologists, which Holland said could include as many as 25 people, is expected to continue that work this summer, beginning on June 1 and lasting through October. Representatives and archaeologists from the Kenaitze Indian Tribe will be present at the site to help with identification.

Other efforts will be concentrated on preparing for the construction of a steel deck arch bridge that will cross Juneau Creek and is expected to take about three years to complete. In building the bridge, Holland said they’re going to start at both sides and meet in the middle. In order to open in 2025, however, access to the bridge on both sides has to be built this summer.

When the project is complete, improvements to transportation in the area will include reconstruction of the east and west ends of the existing roadways, the construction of 10 new miles of roadway north of Cooper Landing and the Kenai River, a new parking lot and trailhead at Resurrection Pass, new intersections at the connection of the new and old roadways, a new bridge that will cross Juneau Creek Canyon and four new wildlife crossing structures. One of those structures will be Alaska’s first wildlife highway overpass.

In all, the project is expected to cost about $375 million with planned completion by 2025. The State of Alaska will cover about 10% of project costs, while the rest will be covered by Federal Highway Trust Funds.

More information about the project can be found on its website at sterlinghighway.net.

Reach reporter Ashlyn O’Hara at ashlyn.ohara@peninsulaclarion.com.

More in News

Various electronics await to be collected and recycled during an electronics recycling event in Seldovia. (Photo courtesy of Cook Inletkeeper)
Cook Inletkeeper celebrates 20 years of electronics recycling

More than 646,000 pounds of electronic waste has been diverted from local landfills.

Liz Harpold, a staff member for Sen. Donny Olson (D-Golovin)​, explains changes to a bill increasing per-student education funding and making various policy changes during a Senate Finance Committee meeting on Thursday, April 24, 2025. (Mark Sabbatini / Juneau Empire)
Revised education bill with $700 BSA hike gets new policy measures, advances to Senate floor

Changes easing charter school rules, adding new district evaluations fall short of governor’s agenda.

Students of Sterling Elementary School carry a sign in support of their school during a special meeting of the Kenai Peninsula Borough School District Board of Education in Soldotna, Alaska, on Wednesday, April 23, 2025. (Jake Dye/Peninsula Clarion)
District adopts budget with severe cuts, school closures

The preliminary budget assumes a $680 increase in per-student funding from the state.

A vote board shows a veto override attempt Tuesday by the Alaska Legislature on a $1,000 increase to per-student education funding falling short of the necessary two-thirds majority with a 33-27 vote. (Mark Sabbatini / Juneau Empire file photo)
Senate adds $700 BSA hike to school phone policy bill a day after veto override on $1,000 increase fails

Lawmakers say quick floor vote by Senate, concurrence by House may set up another override session.

The Soldotna Public Library is seen on a snowy Tuesday, Dec. 27, 2022, in Soldotna, Alaska. (Jake Dye/Peninsula Clarion)
Soldotna library advisory board hears update on federal funding cuts

The federal government’s dismantling of the Institute of Museum and Library Services could cause the reduction or elimination of some statewide library services as soon as July 1.

Protestors stand with an American flag and a sign that reads “DEFUND HATE” on Saturday, April 19 at WKFL Park during the “Sustained Resistence, Makes a Difference” Rally. (Chloe Pleznac/Homer News)
More than 600 gather in Homer for ‘Sustained Resistance, Makes a Difference’ rally

It was at least the third time this year the Homer community gathered to protest the Trump administration.

Sen. Jesse Bjorkman, R-Nikiski, speaks in support overriding Gov. Mike Dunleavy’s veto of House Bill 69 at the Alaska Capitol in Juneau, Alaska, on Tuesday, April 22, 2025. (Mark Sabbatini/Juneau Empire)
Legislature upholds governor’s veto of increased school funding

The governor last week said he vetoed House Bill 69 because it didn’t include any policy changes and because of the state’s “deteriorated” revenue outlook.

Kenai Central High School’s Kyle Foster speaks during the 35th Annual Caring for the Kenai Oral Presentations at Kenai Central High School in Kenai, Alaska, on Thursday, April 17, 2025. (Jake Dye/Peninsula Clarion)
Seward freshman wins 35th Caring for the Kenai with thermal asphalt proposal

Twelve finalists were chosen in this year’s competition.

Gov. Mike Dunleavy (R-Alaska) speaks to reporters about his decision to veto an education funding bill at the Alaska State Capitol on Thursday, April 17, 2025. (Jasz Garrett / Juneau Empire)
Dunleavy’s veto of education funding bill puts pressure on lawmakers during final month of session

Governor also previews new bill with $560 BSA increase, plus additional funds for policy initiatives.

Most Read